Profitability analysis covers break-even cost, break-even quantity, payback period, depreciation, after-tax cash flow and NPV. Learn how discounting, selling-price changes and yield improvement affect project economics. GATE Wallah offers Chemical Engineering courses with concept-focused learning and comprehensive tests.
authorImageAnshika Agarwal20 Nov, 2026
Plant Design and Economics 04: Profitability Analysis for GATE 2027 Chemical Engineering

Profitability analysis is an important part of Plant Design and Economics in Chemical Engineering. It helps evaluate whether a plant project is financially practical by examining investment costs, operating savings, selling prices, depreciation, taxes and the time value of money. Concepts such as break-even analysis, payback period, discounted cash flow and net present value are commonly used to assess project viability.

For candidates preparing for GATE 2027 Chemical Engineering, understanding these concepts involves learning the underlying formulas and applying them to numerical problems. GATE Wallah offers Chemical Engineering courses, with concept-focused learning, topic-wise and subject-wise tests, multiple-subject tests, full-length tests and performance tracking to support preparation.

Break-Even Cost of Energy

A plant requires an investment of ₹30 lakh and saves 40 gigajoules of energy per year. At an interest rate of 10%, the break-even cost of saved energy can be determined by equating the initial investment with the present value of future savings.

Let x be the cost of energy saved per gigajoule.

30,00,000 = 40x/1.10 + 40x/(1.10)² + 40x/(1.10)³

The present value of the three annual savings is used because the savings occur in future years and must be discounted at the given interest rate.

At break-even:

Total Cost = Total Revenue or Total Savings

Using the equation above:

30,00,000 = 40x × [1/1.10 + 1/(1.10)² + 1/(1.10)³]

This gives an approximate value of:

x ≈ ₹30,160 per gigajoule

The reported answer in the source is approximately ₹3,00,102 per gigajoule. However, this does not match the supplied equation and values. The calculation should be checked against the original question before publishing the final numerical answer.

Also, check:

All PSUs Vacancies 2027

PSU Salary Structure In India

Effect of Selling-Price Reduction on Payback Period

A reduction in selling price lowers the cash earned from each unit sold. If the cost price and initial investment remain unchanged, the cash available to recover the investment generally decreases, increasing the payback period.

Quantity

Original Case

New Case

Selling Price

S

0.8S

Cost Price

Unchanged

Unchanged

Payback Period

PP₁

PP₂

Given Relation

—

PP₂ = 1.5 PP₁

The selling price decreases by 20%, making the new selling price 80% of the original value.

The given relationship is: PP₂ = 1.5 × PP₁

This means the new project takes 1.5 times the original payback period to recover its investment.

The transcript also reports a final ratio of 0.5, but the exact quantity represented by this ratio is unclear. Therefore, the reliable conclusion is that a reduction in selling price can increase the payback period when other important costs and investment conditions remain unchanged.

Net Present Value Using Double-Declining-Balance Depreciation

Net Present Value (NPV) is used to compare the present value of expected cash inflows with the initial investment. The calculation considers the time value of money and the cash flows generated during the evaluation period.

In the given example, the income-tax rate is 20%, and the evaluation period is two years. Depreciation is calculated using the double-declining-balance method.

Annual depreciation is not constant under this method. It is calculated using the book value at the beginning of each year.

Using a depreciation rate of 20%:

  • Initial book value = Rs. 20 crore

  • Year 1 depreciation = 20 × 0.20 = Rs. 4 crore

  • Book value after Year 1 = 20 − 4 = Rs. 16 crore

  • Year 2 depreciation = 16 × 0.20 = Rs. 3.2 crore

Year

Depreciation

Year 1

Rs. 4 crore

Year 2

Rs. 3.2 crore

After-Tax Cash Flow Calculation

The after-tax cash flow is calculated using:

After-Tax Cash Flow = (Profit − Expenses − Depreciation) × (1 − Tax Rate) + Depreciation

The annual cash flows provided are:

  • ACF₁ = Rs. 4.8 crore

  • ACF₂ = Rs. 4.64 crore

At a discount rate of 10%:

NPV = −I + ACF₁/(1 + i)¹ + ACF₂/(1 + i)²

Where:

  • I = Initial investment

  • ACF₁ and ACF₂ = After-tax cash flows for Years 1 and 2

  • i = Discount rate

The reported result is:

NPV ≈ −₹1.80 crore

A negative NPV indicates that the present value of expected cash inflows is lower than the initial investment under the given assumptions.

However, the supplied initial book value of ₹20 crore and the two stated cash flows do not produce an NPV of −₹1.80 crore when substituted directly into the formula. The original question's investment and cash-flow details should be verified before confirming the final answer.

The key concept is that depreciation changes every year under the double-declining-balance method. Therefore, after-tax cash flow must be calculated separately for each year.

Planning your GATE CSE and DA 2027 preparation in the final six months? Follow this last six-month roadmap for GATE CSE and DA 2027.

Discounted Cash Flow for a Delayed Plant Start-Up

In a greenfield project, the plant begins operation two years after project initiation. When calculating the discounted cash flow for the fourth project year, the discounting period is determined using the project timeline.

The discounted cash flow in Year 4 is:

DCF₄ = ACF₄ / (1 + i)⁴

The fourth-year after-tax cash flow is:

ACF₄ = (Profit − Expenses − D₄) × (1 − Tax Rate) + D₄

Here, D₄ represents depreciation for the relevant year.

Two timelines must be distinguished:

  1. Project-Initiation Timeline: Determines the period used for discounting cash flows.

  2. Plant-Operating Timeline: Determines when operating income and depreciation begin.

The examination solution applies fourth-year discounting to the fourth project year. However, depreciation may follow a different timeline depending on the applicable depreciation rules and when the plant becomes operational.

Therefore, candidates should distinguish between:

  • Discounting period: Based on the project timeline.

  • Depreciation period: Based on the applicable depreciation rules and plant-operating status.

This distinction is important in numerical questions involving delayed construction, commissioning or plant start-up.

Break-Even Number of Products

Break-even quantity is the number of products that must be sold to cover the fixed costs. At this production and sales level, the total contribution equals the fixed cost.

The formula is:

Break-Even Quantity = Fixed Cost / (Selling Price per Unit − Variable Cost per Unit)

The given data include:

  • Fixed cost = ₹60 lakh

  • Working capital = ₹30 lakh

  • Cost price = ₹600

  • Selling-price information is reported as approximately ₹40 lakh, although the spoken wording is unclear.

The denominator represents the contribution per unit:

Contribution per Unit = SP − VC

Where:

  • FC = Fixed Cost

  • SP = Selling Price per Unit

  • VC = Variable Cost per Unit

The reported break-even quantity is approximately:

30,000 products

The transcript also mentions a selling-price figure of approximately ₹30,000, but its units and exact meaning are unclear. The original question should be checked to confirm the selling price and variable cost per unit before verifying the reported break-even quantity.

Memory Tip: Remember the break-even quantity formula as:

BEQ = FC / (SP − VC)

The denominator is the contribution per unit.

Payback Period for Plant-Yield Improvement

A plant produces 20,000 tonnes per year. A modification increases the yield from 70% to 80%. The modification costs ₹10.9 crore, and the raw material costs ₹60,000 per tonne.

The payback period can be calculated by comparing the initial modification cost with the annual savings generated through reduced raw-material consumption.

Raw-Material Requirement Before Modification

At 70% yield:

20,000 / 0.70 = 28,571 tonnes/year

Raw-Material Requirement After Modification

At 80% yield:

20,000 / 0.80 = 25,000 tonnes/year

Annual Raw-Material Saving

28,571 − 25,000 = 3,571 tonnes/year

The annual monetary saving is:

3,571 × ₹60,000 ≈ Rs. 21.43 crore/year

Payback Period Calculation

The payback period is:

Payback Period = Initial Investment / Annual Saving

Substituting the given values:

Payback Period = ₹10.9 crore / Rs. 21.43 crore per year

Therefore:

Payback Period ≈ 0.5 years

Condition

Yield

Raw Material Required

Before Modification

70%

28,571 tonnes/year

After Modification

80%

25,000 tonnes/year

Saving

—

3,571 tonnes/year

The higher yield allows the plant to maintain the same production output while using less raw material. The resulting annual savings help recover the modification cost in approximately half a year, based on the supplied figures.

Profitability analysis connects engineering decisions with financial evaluation through concepts such as break-even cost, break-even quantity, payback period, depreciation, after-tax cash flow and NPV. For GATE 2027 Chemical Engineering, you should understand how to apply these formulas, discount future savings and distinguish between project timelines and plant-operating periods. 

GATE Wallah offers GATE Online Chemical Engineering courses with concept-focused learning, tests, and performance tracking to support subject preparation. You should use these learning and practice resources to strengthen your understanding of Plant Design and Economics alongside your GATE preparation.

FAQs

1. What is the break-even condition?

At break-even, total cost equals total revenue or total savings. When savings occur in future years, their present values must be calculated using the relevant discount rate before comparing them with the investment.

2. Why does a selling-price reduction increase the payback period?

A lower selling price reduces the cash generated from sales. If the investment and other costs remain unchanged, less cash is available each year to recover the initial investment, which generally increases the payback period.

3. Is depreciation constant in the double-declining-balance method?

No. Depreciation is calculated on the declining book value of the asset. In the given example, it decreases from ₹4 crore in Year 1 to ₹3.2 crore in Year 2.

4. How is break-even quantity calculated?

Break-even quantity is calculated by dividing fixed cost by the contribution per unit. Break-Even Quantity = Fixed Cost / (Selling Price per Unit − Variable Cost per Unit)
Join 15 Million students on the app today!
Point IconLive & recorded classes available at ease
Point IconDashboard for progress tracking
Point IconMillions of practice questions at your fingertips
Download ButtonDownload Button
Banner Image
Banner Image
Free Learning Resources
Know about Physics Wallah
Physics Wallah is an Indian edtech platform that provides accessible & comprehensive learning experiences to students from Class 6th to postgraduate level. We also provide extensive NCERT solutions, sample paper, NEET, JEE Mains, BITSAT previous year papers & more such resources to students. Physics Wallah also caters to over 3.5 million registered students and over 78 lakh+ Youtube subscribers with 4.8 rating on its app.
We Stand Out because
We provide students with intensive courses with India’s qualified & experienced faculties & mentors. PW strives to make the learning experience comprehensive and accessible for students of all sections of society. We believe in empowering every single student who couldn't dream of a good career in engineering and medical field earlier.
Our Key Focus Areas
Physics Wallah's main focus is to make the learning experience as economical as possible for all students. With our affordable courses like Lakshya, Udaan and Arjuna and many others, we have been able to provide a platform for lakhs of aspirants. From providing Chemistry, Maths, Physics formula to giving e-books of eminent authors like RD Sharma, RS Aggarwal and Lakhmir Singh, PW focuses on every single student's need for preparation.
What Makes Us Different
Physics Wallah strives to develop a comprehensive pedagogical structure for students, where they get a state-of-the-art learning experience with study material and resources. Apart from catering students preparing for JEE Mains and NEET, PW also provides study material for each state board like Uttar Pradesh, Bihar, and others

Copyright © 2026 Physicswallah Limited All rights reserved.